Du Quartier Boulevard

 

Work to widen boulevard Du Quartier is planned for summer 2018 through summer 2019.

Project Overview

  • Between boulevard Lapinière and Grande Allée
  • Works at the Lapinière intersection
  • Three lanes in each direction, central median
  • Reserved lanes for public transit (RTL)
  • Grass to be laid
  • Unidirectional bicycle paths on both sides
  • Sidewalks on both sides
  • Lighting and traffic lights


Map of municipal projects in the C section (Available in French - click to enlarge)
 


Panneau_Municipaux_LR.jpg

Timetable*
 

  • Start of worls: summer 2018
  • Paving and curbs: summer - fall 2018
  • Completion of the paving: spring - summer 2019
  • Bicycle paths and sidewalks: summer 2018 - summer 2019
  • End of works: summer 2019
 

*IMPORTANT: The timetable is prensented as a guide and is subject to change due to weather conditions or unforseen events encountered during the work.

LOGO_InfoTravaux_Noir02.jpg
Follow the project’s progress in the Urban Infrastructures section | C section - TOD Quartier, of the Info-Travaux page on our web site. 
 
Comments, Suggestions and Questions
Do you have a comment, a suggestion or a question about this project? Email us at services@brossard.ca.


Click to enlarge